Technical Details: An Architect’s Guide To Level Thresholds
CategoriesArchitecture

Technical Details: An Architect’s Guide To Level Thresholds

Emma Walshaw is the founder of First In Architecture and Detail Library. She has written a number of books aiming to facilitate a better understanding of construction and detailing. First In Architecture is a website providing resources and guides for architects and students. 

Level thresholds can be very difficult to detail, with many standard details always showing a 150 mm step between the finished floor level and external ground level. However, level thresholds provide a future-proof solution to an aging population and ensure a building can be used and visited by everyone. They are also a very aesthetic solution to bridging the gap between indoors and outdoors.

Level thresholds are also a legal requirement for new build housing in the UK. This means that all external doors, front, rear and side, plus any sliding, bifold, French or terrace doors, must provide a level entrance and exit. Although it is not a building regulation requirement in renovation projects, some councils may require level thresholds as a planning condition within extensive renovation projects.

Below we look at key considerations when designing level thresholds to ensure water does not enter the building.

Bienville House by Nathan Fell Architecture, New Orleans, LA, United States

Accessible / Level Threshold

An accessible threshold is defined as a threshold this is level or, if raised, has a total height of not more than 15 mm, a minimum number of upstands and slopes and with any upstands higher than 5 mm chamfered.

Building Regulation Requirements

For single new build properties, Building Regulation Part M4(1) and M4(2) must be met. This requires all access to the dwelling to be step free, including the entrance, garden and any terraces. For larger developments or flats, the local council may require 10% of units to meet Building Regulations Part M4(3), meaning the unit is fully adaptable to a wheelchair user.

Whilst these Building Regulations do not need to be met in the case of an extension, some Local Authorities, Building Control and/or Approved Inspectors may require the need to meet Part M4(1) within a planning approval condition, requiring entrances and exits to the house to be accessible.

Ground Floor Thresholds

LHS – In-situ concrete threshold drain built under the sill and pavers, pavers to be removable or inspection hatch to be provided at either end of the drain for cleaning and maintenance.

RHS – Aluminum threshold drain installed between pavers and sill with removable grill for inspection, drain with low level water entry of water infiltration between drain and sill.

There are various ways of designing a level threshold based on aesthetic, cost, structure, site conditions and location. However, there are a number of key features that all level thresholds should take into account.

Door — When specifying a door to be used in a level threshold, most manufacturers will state if the system is compliant with Part M of the Building Regulations. This guarantees that the element you step over is no more than a maximum 15 mm in height with no upstands of more than 5mm. Most sliding door manufactures provide frames with a completely level base frame. However, it is important to check the base frame of elements such as front and rear doors, especially in timber, as these will need special aluminum thresholds to be fully accessible.

Threshold Drainage — This is a building regulations requirement when designing this type of threshold. A drain can be installed between the sill and external landscaping flush with the level floor or hidden under the finishes. Many door manufacturers will even be able to provide a threshold drain for the door system chosen. This will help drain away any water near the drain as well as water which hits the door or glass and drains through the frame.

Threshold drain designed to clip into the aluminum sliding door system to drain both surface rain and rain hitting the glass and filtering through the window frame.

Waterproofing — Damp proof membranes should be draped up the door or window frame system at the point of the threshold. Water should be moved away from the threshold, by sloping eternal finishes away from the drain. To either side of the threshold, the damp proof course should be minimum of 150mm above ground level.

Key Points To Remember

  • The threshold — including the door frame — should not be more than 15 mm in height overall. Of these 15 mm, there should be a minimum number of upstands and slopes, with any upstands higher than 5 mm chamfered.
  • If the threshold is exposed to wind driven rain the landing can be up to 10 mm below the level of the sill if the sill is rounded or chamfered.
  • The external landing should have a fall ratio of between 1:40 and 1:60.
  • Ensure all water falls away from the doorway in a single direction.
  • Build a drainage channel between the landing and the threshold.
  • Ensure the channel discharges to a drainage system or land drainage such as a soakaway.

Timber Frame Key Considerations

LHS – Timber frame construction either side of threshold showing concrete slab construction and raised foundation blocks 150 mm above finished floor level, with threshold drain.

RHS – Level threshold with drain

Usually when designing for a timber frame structure, the timber frame should begin 150 mm above the ground level. This concept should be maintained when the ground level externally is level with the internal finish floor level. All the same considerations as above should be taken to account as well as the foundation or timber structure being raised 150 mm above the external ground level, usually 150 mm higher than the internal finished floor level.

Raised Terrace

Another way of preventing water ingress at this critical junction is to use a raised terrace such as paving slabs on pedestals. Whilst this is the best option if you have a raised terrace area, it is also used when the garden level is lower that your internal ground floor level, such as with a beam and block construction. Further details can be found in the following section.

Level Balcony and Terrace Thresholds

When designing a level threshold onto a raised terrace or balcony, even more care needs to be taken to assure that water does not enter the building fabric.

When creating a level threshold over a heated space, care needs to be taken when setting the internal finish floor level and ceiling level to allow for the new insulation. Many people opt for vacuum insulation to this area to allow for a reduced terrace build-up.

Adjustable pedestals can be used to bridge the gap between the level pavers or timber deck with the sloped flat roof. The gaps between the deck material is also key in allowing the water to drain through to the roof and the roof outlet.

Key Points To Remember

  • The threshold including door frame should not be more than 15mm in height overall. Of these 15mm, there should be a minimum number of upstands and slopes, with any upstands higher than 5mm chamfered.
  • The gap between door sill and paving or timber to be a minimum of 10mm.
  • The gap between paving or timber to be a minimum of 6mm.
  • Flat roof to have 1:40 falls for a 1:80 minimum built slope.
  • Ensure all water falls away from the doorway in a single direction.
  • Build a drainage outlet on the opposite side of the flat roof to the threshold.
  • Ensure the flat roof has an overflow.
  • Ensure all waterproofing has a minimum of 75mm upstand under the threshold.
  • Provide a minimum 150mm waterproofing upstand to sides such as brickwork.

Bienville House by Nathan Fell Architecture, New Orleans, LA, United States

Resources

If you want more inspiration on level thresholds, detailing and precedents, be sure to follow Detail Library on Pinterest where we have lots of examples.

For more information on how to detail level and accessible thresholds check out the fully resolved details on The Detail Library.

Top image: Canyon Run by Migration Studios, Concept

 The Fourth Annual One Drawing Challenge is open for entries! Architecture’s most popular drawing competition is back and bigger than ever, including larger prizes. Get started on your submission and hurry — the Main Entry Deadline of October 21st is fast-approaching.  

Reference

Enscape 3.3 Takes Real-Time Architectural Visualization to the Next Level
CategoriesArchitecture

Enscape 3.3 Takes Real-Time Architectural Visualization to the Next Level

Enscape, one of architecture’s most popular real-time visualization, 3D rendering and virtual reality applications, just got even better. Its latest iteration, version 3.3, brings a plethora of enhancements for its existing features as well as a host of new functions, each designed to make real-time rendering more intuitive to use at every stage of the design process.

Enscape brings the disciplines of design and visualization together, creating a unified experience that enables designers to collaborate on their projects in a dynamic fashion, as well as communicating their ideas to clients in an easy-to-understand way.

“We’re always looking for new ways to support our customers’ design workflows,” said Petr Mitev, VP Visualization Product Group at Enscape. “With our latest release, we’ve automated some processes so designers can spend more time making the right decisions and less time gathering the data needed to do it. We will also continue to improve our core visualization and sharing platforms based on community feedback.”

So, what can users expect from the new and improved Enscape application? Here are some key new features to look out for:


Site Context

It’s now possible to import a project’s existing surroundings directly into renderings, using data from global geographic database OpenStreetMap. Users can enter a specific address or coordinates to immediately locate and import the surroundings, or select and import key landmarks, streets, or topography.


Alpha Channel Export

With the Alpha Channel Export, you can now render an image with a transparent background. This means your project can now be quickly and easily combined with any style of sky, clouds, and horizon line in post production, lending Enscape a new layer of flexibility for still renderings.


Education Assets and Materials

Enscape’s popular 3D asset library has been radically expanded to include an extensive collection of educational assets, including classroom furniture, toys, musical instruments, playground equipment, acoustic panels, and more. The Enscape Material Library, which was introduced in Enscape 3.1, has also been expanded with materials such as new wallpapers and various carpets.

While they will be categorized under Education and are perfectly suited for kindergarten, school and college projects, these assets and materials are also useful for a wide variety of other typologies, including corporate, hospitality and residential projects.

Besides these headline new features, numerous other refinements have been introduced to Enscape 3.3, each with the goal of improving ease-of-use and an improved end product for users.


Additional Features

In terms of rendering, visualizations including glass and water are now more accurate thanks to improved graphic capabilities; transparent materials now appear in reflections, providing a more realistic appearance. The use of a graphics card that supports hardware-accelerated ray tracing, such as NVIDIA RTX series and AMD RX6xxx series, is required. Further to this, the new “Material Overwrite” function enables users to replace Enscape material files within the Enscape Material Editor without the need to manually import and export them.

In terms of user experience, it’s now possible to ‘pin’ the Enscape rendering window and associated menus to the top of your modeling window, allowing for easy access to view real-time changes even if you’re not using two screens. New upload migration capabilities have also been introduced, enabling users to manage uploads, such as web standalones and uploaded panoramas, online efficiently.

Finally, Enscape 3.3 works seamlessly with the latest version of SketchUp, providing key compatibility with one of the industry’s most used 3D modeling applications. Throw in full Japanese language support, and the latest edition of Enscape is inarguably the most comprehensive release to date when it comes to usability across platforms and geographies.

To get a first-hand look at Enscape’s full suite of real-time capabilities, click here to download a 14-day free trial. You can find out more about every feature over at Enscape.com.

Reference